Shenyang-Dandong Passenger Line Railway

3(1)

Shenyang-Dandong Passenger Line Railway

2023-10-18

Constructed by: China State Construction Engineering Corp.Ltd


Specifications: It not only adds one more option from Shenyang to Dandong, but also shortens the time from 3 hours to 40 minutes, which makes Dandong into “One-hour enconomic circle”of Shenyang City.The total length of Shenyang-Dandong Passenger Line is 207km and estimated invested budget is 26.7billion.The designed speed is 250km/h. The key projects of Shenyang-Dandong Passenger Line are: Four bridges,three tunnels and one station.


Product Used: Formtraveler


Solution:40+64+40m continuous beam,Length of #0 segment:9m, Longest segment:4.25m,Heaviest concrete segment:150.2T.